Contact

Staci A. West
Communications Manager
sawest@bechtel.us

Angie Brotherton
Deputy Comms Manager
acbrothe@bechtel.us

Newsroom

Share This Page

Waste Treatment Plant continues startup progress

Media Library

Social Media

Latest News

Fundraiser Kicks Off School Year for 200 Kids

August 25, 2026

Read More

Partnerships Key to Progress at Hanford’s High-Level Waste Facility

July 21, 2026

Read More

Bechtel Donates to Boys & Girls Clubs to Support Students’ College Exploration

July 13, 2026

Read More

Bechtel Helps Launch New All-Abilities Theatre Program

July 8, 2026

Read More

Over 100,000 Gallons of Hanford Tank Waste Turned to Glass

May 18, 2026

Read More

Vit Plant Team Transitions from Readiness to Results

April 21, 2026

Read More
RICHLAND, Wash. Dec 19, 2017

Waste Treatment Plant continues startup progress

A Startup electrician safely opens a utility systems control panel at Hanford’s Waste Treatment and Immobilization Plant. Workers have transferred 70 percent of utility systems from the construction phase to the startup phase.
A Startup electrician safely opens a utility systems control panel at Hanford’s Waste Treatment and Immobilization Plant. Workers have transferred 70 percent of utility systems from the construction phase to the startup phase.

Workers at Hanford’s Waste Treatment and Immobilization Plant (WTP) have completed the startup and testing phase for 20 percent of the utility systems needed to support future plant operations.

This work is progressing on an extensive array of process support infrastructure called the plant’s Balance of Facilities (BOF).

“We’re making strong, early progress in starting up, testing, and preparing the industrial utility services that will support WTP,” said Kim Irwin, Bechtel National Inc. (BNI) project manager for WTP. “As engineers and construction crews finish portions of the utilities, they transfer those systems to the startup phase where we verify they are complete, tested, and in safe and working order.”

To prepare the 65-acre site for eventual operations, the U.S. Department of Energy’s Office of River Protection and WTP contractor BNI are coordinating a concurrent construction, startup, and commissioning approach with the goal of safely beginning treatment of Hanford’s low-activity radioactive tank waste as soon as 2022.

This support infrastructure is housed in 20 BOF support buildings. BOF contains a total of 56 systems, including an electrical power distribution system, backup power, water purification, compressed air, steam, communication and control, and fire water systems.

Of the 56 systems, 11 have successfully completed startup and testing and have transitioned over to the commissioning phase; 28 are in the startup phase; and 17 are nearing construction turnover to startup. This equates to 70 percent of utility systems that workers have transferred from the construction phase to the startup phase.

Currently, startup crews are focused on testing WTP’s electrical and water-distribution systems.

“As systems and subsystems are completed there is a rigorous ‘construction turnover to startup’ that takes place over several weeks where walk-downs, physical inspections, and documentation happen,” said Bill Hamel, WTP Federal Project Director for ORP.

After the startup phase, systems undergo a commissioning phase to ensure they are calibrated and ready to support future plant operations. All WTP facilities, including the Low-Activity Waste (LAW) Facility and the Analytical Laboratory (LAB), will undergo the startup and commissioning process currently underway in the less complicated BOF systems.

The WTP Project is working to begin treating Hanford’s low-activity tank waste as soon as 2022 through DOE’s Direct Feed Low-Activity Waste (DFLAW) approach. Nearly all primary components and equipment are installed in the LAW Facility and the facility is on track to complete construction in 2018.

Meanwhile, construction crews continue to work on completing construction of the LAW facility, making minor modifications to LAB systems to support DFLAW operations, and finishing the remaining BOF support systems. Once completed, these remaining systems will transition into the startup phase to support DFLAW.

About the Office of River Protection

Bechtel is a trusted engineering, construction and project management partner to industry and government. Differentiated by the quality of our people and our relentless drive to deliver the most successful outcomes, we align our capabilities to our customers’ objectives to create a lasting positive impact. Since 1898, we have helped customers complete more than 25,000 projects in 160 countries on all seven continents that have created jobs, grown economies, improved the resiliency of the world’s infrastructure, increased access to energy, resources, and vital services, and made the world a safer, cleaner place. Bechtel serves the Infrastructure; Nuclear, Security & Environmental; Oil, Gas & Chemicals; and Mining & Metals markets. Our services span from initial planning and investment, through start-up and operations. www.bechtel.com