Vit Plant Prepares for Melter Heatup, Begins Installing Startup Heaters

The weather isn’t the only thing heating up at the Hanford Site this summer, as staff at the Low-Activity Waste (LAW) Facility at the Vit Plant are preparing to install 18 temporary heaters to start up the first of the facility’s two 300-ton glass melters.

The startup heaters will be installed through ports in the lid of the melter and will raise the melter’s internal operating temperature to 2,100 degrees Fahrenheit — hot enough to sustain the pool of molten glass to be used to start the waste vitrification process.

“This is an exciting and important step for our team as we drive toward melter heatup,” said Vit Plant Project Director Valerie McCain. “The melters are the heart of the Direct-Feed Low-Activity Waste (DFLAW) Program and bringing Melter 1 online is a significant milestone on our journey to begin treating tank waste.”

Heating up the melter is a complex process, consisting of a series of activities to prepare for and establish the pool of molten glass. After the startup heaters raise the melter to operating temperature, small glass beads called frit will be added until the pool covers the heating electrodes inside the melter.

After melter heatup, the startup heaters will be removed and replaced with bubblers to mix the molten glass pool and help maintain an even temperature. Finally, more frit will be added to the melter to bring the pool up to operating level. The melter will then be ready to receive simulated materials to test the system before processing tank waste.

During DFLAW operations, waste from Hanford’s large underground tanks that has been treated to remove radioactive cesium and solids will be fed directly to the LAW Facility’s melters. The waste and glass-forming materials will be mixed and heated in the melters, then poured into specially designed stainless-steel containers for permanent disposal at the site’s Integrated Disposal Facility.

Contact: Staci A. West, 509-378-0308 or sawest@bechtel.com

About Bechtel National Inc.:

Bechtel is a trusted engineering, construction and project management partner to industry and government. Differentiated by the quality of our people and our relentless drive to deliver the most successful outcomes, we align our capabilities to our customers’ objectives to create a lasting positive impact. Since 1898, we have helped customers complete more than 25,000 projects in 160 countries on all seven continents that have created jobs, grown economies, improved the resiliency of the world's infrastructure, increased access to energy, resources, and vital services, and made the world a safer, cleaner place. Bechtel serves the Infrastructure; Nuclear, Security & Environmental; Oil, Gas & Chemicals; and Mining & Metals markets. Our services span from initial planning and investment, through start-up and operations. www.bechtel.com