Crews at the Hanford Vit Plant have poured the first test glass from a second melter into a stainless-steel container in the plant’s Low-Activity Waste (LAW) Facility.

“Plant crews have demonstrated that both melters are fully operational and capable of pouring glass,” said Mat Irwin, U.S. Department of Energy Office of Environmental Management acting assistant manager for WTP. “System tests will begin to look more like future waste treatment operations moving forward.”

Plant personnel will continue to pour glass from Melter 2 in batches so control room staff can practice the process until they have filled the container. The Vit Plant produced the first container of test glass last year after completing a similar series of pours from Melter 1.

Personnel heating up melters and pouring test glass are an important part of commissioning the facility to prepare for vitrifying, or immobilizing in glass, millions of gallons of radioactive and chemical waste from Hanford’s large underground tanks.

“The first pour from Melter 2 is another important step in commissioning the plant and preparing for the future sustained production of vitrified waste,” said Brian Hartman, senior vice president for Bechtel National Inc., lead contractor for the Vit Plant. “I’m proud of our team’s progress in heating a second melter, managing other first-time systems and moving forward with filling more containers.”

During future waste treatment operations, Hanford crews will feed waste from underground tanks that have been treated to remove radioactive solids and cesium to the melters inside the LAW Facility. The waste will be mixed with glass-forming materials in the melters, then poured into specially designed stainless-steel containers for disposal at Hanford’s Integrated Disposal Facility.

About the Vit Plant

In southeastern Washington state, Bechtel National, Inc. is designing, constructing, and commissioning the world’s largest radioactive waste treatment plant for the U.S. Department of Energy (DOE). When complete, the Hanford Tank Waste Treatment and Immobilization Plant, also known as the Vit Plant, will process and stabilize millions of gallons of radioactive and chemical waste currently stored at the Hanford Site.

About Bechtel

Bechtel is a trusted engineering, construction and project management partner to industry and government. Differentiated by the quality of our people and our relentless drive to deliver the most successful outcomes, we align our capabilities to our customers’ objectives to create a lasting positive impact. Since 1898, we have helped customers complete more than 25,000 projects in 160 countries on all seven continents that have created jobs, grown economies, improved the resiliency of the world's infrastructure, increased access to energy, resources, and vital services, and made the world a safer, cleaner place. Bechtel serves the Infrastructure; Nuclear, Security & Environmental; Oil, Gas & Chemicals; and Mining & Metals markets. Our services span from initial planning and investment, through start-up and operations. www.bechtel.com