Vit Plant Completes Key Safety System Testing
Workers at the Vit Plant have completed testing key safety systems inside the plant’s Low-Activity Waste Facility, moving the facility toward commissioning to support the Direct-Feed Low-Activity Waste Program to immobilize tank waste in glass.
The tests are part of ongoing efforts to verify the ability of the LAW Facility emissions treatment system to respond to potential issues. The LAW Facility contains 37 secondary safety systems, each responsible for addressing different scenarios.
“These secondary safety systems help prevent an unlikely, unplanned event,” said Mat Irwin, Hanford’s acting assistant manager for the Vit Plant Project. “The testing verified that the systems’ hardware and software work in unison, a key step in helping ensure operational safety at the LAW Facility.”
During the tests, workers electronically triggered each system to simulate a response to a pressure change, and carefully monitored and documented response times. The tests simulated scenarios of excessive or insufficient air pressure within the emissions treatment system.
“These tests required careful synchronization among 45 crew members spread across eight zones inside the LAW Facility,” said Rick Holmes, Bechtel National Inc. principal vice president and general manager for Waste Treatment Completion Company. “Together they ensured that technical requirements of the tests were met, while also ensuring safety standards were maintained throughout.”
The completion of these tests moves the facility closer to fully demonstrating the reliability of its safety systems and ensures the emissions treatment system is ready for the next stages of operation.
About the Vit Plant
In southeastern Washington state, Bechtel National, Inc. is designing, constructing, and commissioning the world’s largest radioactive waste treatment plant for the U.S. Department of Energy (DOE). When complete, the Hanford Tank Waste Treatment and Immobilization Plant, also known as the Vit Plant, will process and stabilize millions of gallons of radioactive and chemical waste currently stored at the Hanford Site.
Bechtel is a trusted engineering, construction and project management partner to industry and government. Differentiated by the quality of our people and our relentless drive to deliver the most successful outcomes, we align our capabilities to our customers’ objectives to create a lasting positive impact. Since 1898, we have helped customers complete more than 25,000 projects in 160 countries on all seven continents that have created jobs, grown economies, improved the resiliency of the world's infrastructure, increased access to energy, resources, and vital services, and made the world a safer, cleaner place. Bechtel serves the Infrastructure; Nuclear, Security & Environmental; Oil, Gas & Chemicals; and Mining & Metals markets. Our services span from initial planning and investment, through start-up and operations. www.bechtel.com