Contact

Staci A. West
Communications Manager
sawest@bechtel.us

Angie Brotherton
Deputy Comms Manager
acbrothe@bechtel.us

Newsroom

Share This Page

Key strategy helps Vit Plant support building take shape

Media Library

Social Media

Latest News

Fundraiser Kicks Off School Year for 200 Kids

August 25, 2026

Read More

Partnerships Key to Progress at Hanford’s High-Level Waste Facility

July 21, 2026

Read More

Bechtel Donates to Boys & Girls Clubs to Support Students’ College Exploration

July 13, 2026

Read More

Bechtel Helps Launch New All-Abilities Theatre Program

July 8, 2026

Read More

Over 100,000 Gallons of Hanford Tank Waste Turned to Glass

May 18, 2026

Read More

Vit Plant Team Transitions from Readiness to Results

April 21, 2026

Read More
RICHLAND, Wash. Oct 31, 2018

Key strategy helps Vit Plant support building take shape

Vit Plant employees prepare to lift a 40-ton process cell pipe rack into the effluent management facility.
Vit Plant employees prepare to lift a 40-ton process cell pipe rack into the effluent management facility.

Being in two places at once became a key strategy for Hanford Vit Plant employees in maintaining an aggressive construction schedule at the effluent management facility (EMF).

Employees recently installed two 40-ton process cell pipe racks into EMF that were constructed across the parking lot and pre-loaded with more than 3,000 linear feet of pipe and nearly 200 linear feet of cable tray. While those racks were being built over the past several months, another team was inside the facility making progress on special protective concrete coatings, process pump installations, and equipment installations.

Because of the congested footprint of the facility during the construction phase of EMF, completing scope outside of the building using modular construction concepts – a strategy widely used on other global Bechtel projects – allowed for concurrent construction that would have otherwise been completed in series.

This key strategy has reduced congestion risk and allowed timely progress on the final Vit Plant support building required to deliver the direct feed low-activity waste (DFLAW) vitrification approach.

The pipe racks are steel structures that will allow utilities to be run between areas of the facility to connect equipment and systems. Each rack measures roughly 25-feet tall, 20-feet wide, and 70-feet long and required the team to work a 16-hour shift with a heavy lift crane on the day of final installation. After the rack modules were flown into the main process facility, workers began bulk pipe installations within the building footprint.

During low-activity waste vitrification operations, secondary liquids will be generated from the melter off-gas system. These liquids will go to EMF where excess water will be evaporated away and transferred to Hanford’s Liquid Effluent Retention Facility, while the remaining concentrate sent back into the vitrification process.