Contact

Staci A. West
Communications Manager
sawest@bechtel.us

Angie Brotherton
Deputy Comms Manager
acbrothe@bechtel.us

Newsroom

Share This Page

Hanford Waste Treatment Plant installs 85-ton shield door

Media Library

Social Media

Latest News

Fundraiser Kicks Off School Year for 200 Kids

August 25, 2026

Read More

Partnerships Key to Progress at Hanford’s High-Level Waste Facility

July 21, 2026

Read More

Bechtel Donates to Boys & Girls Clubs to Support Students’ College Exploration

July 13, 2026

Read More

Bechtel Helps Launch New All-Abilities Theatre Program

July 8, 2026

Read More

Over 100,000 Gallons of Hanford Tank Waste Turned to Glass

May 18, 2026

Read More

Vit Plant Team Transitions from Readiness to Results

April 21, 2026

Read More
Richland WA Dec 31, 2010

Hanford Waste Treatment Plant installs 85-ton shield door

Richland, Wash. — Today, crews at the Hanford Waste Treatment Plant lifted an 85-ton shield door into the largest of its four major nuclear facilities — the Pretreatment Facility. The carbon steel door measures 15 feet wide, 27 feet tall and 10 inches thick; it was lowered through the roof into the canyon-center of the facility. A 102-ton door is scheduled to be set above this door next month.

Bechtel National, Inc. is designing and building the world’s largest radioactive waste treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern Washington state. The $12.2 billion Waste Treatment and Immobilization Plant (WTP), also known as the “Vit Plant,” will immobilize the radioactive liquid waste currently stored in 177 underground tanks using a process called “vitrification.”

Vitrification involves blending the waste with molten glass and heating it to high temperatures. The mixture is then poured into stainless steel canisters. In this glass form, the waste is stable and impervious to the environment, and its radioactivity will dissipate over hundreds to thousands of years.

The WTP will cover 65 acres with four nuclear facilities — Pretreatment, Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical Laboratory — as well as operations and maintenance buildings, utilities and office space.

Construction of the WTP began in 2001 and is now 58 percent complete. Construction is scheduled to be complete in 2016 and operational in 2019.