hanford vitrification plant
Project progress update
Total project: 63% complete (as of January 22, 2012)
-
86% design complete
-
64% procurement complete
-
60% construction complete

Pretreatment Facility
World’s largest radioactive chemical separations facility
-
80% design complete
-
51% procurement complete
-
42% construction complete

High-Level Waste Vitrification Facility
Turns high-level waste into glass
-
88% design complete
-
74% procurement complete
-
39% construction complete

Low-Activity Waste Vitrification Facility
Turns low-activity waste into glass
-
89% design complete
-
86% procurement complete
-
68% construction complete

Analytical Laboratory
Ensures glass meets regulatory requirements
-
81% design complete
-
75% procurement complete
-
77% construction complete

Balance of Facilities — 18 support facilities and underground utilities
Vast infrastructure to support operations
-
77% design complete
-
47% procurement complete
-
63% construction complete
A bit of perspective
-
Plant construction requires approximately 263,000 cubic yards of concrete — enough to fill 26,300 concrete trucks.
-
Plant construction requires more than 930,000 feet of piping; if laid end-to-end, it would stretch more than 170 miles — approximately the distance from Seattle, Wash., to Portland, Ore.
-
Plant construction requires more than 40,000 tons of structural steel, enough to build the equivalent of three Eiffel Towers.
-
Plant construction requires more than 5,000,000 feet of cable and wire; if laid end-to-end, it would stretch nearly 900 miles, more than the distance from Seattle, Wash., to Salt Lake City, Utah.