hanford vitrification plant

Hanford Waste Treatment and Immobilization Plant completes complex door liner installation

Tue, June 16, 2009

Richland, Wash. — Today, crews at the Hanford Waste Treatment and Immobilization Plant (WTP) lifted a massive door liner into place in the High-Level Waste (HLW) Vitrification Facility, demonstrating continued progress at the Vit Plant.

This is a significant accomplishment for the HLW Facility and the Vit Plant as a whole,” Ty Troutman, area project manager for the …

continue story

Hanford Waste Treatment Plant piping protection system put into service

Thu, April 2, 2009

Richland, Wash. — The Hanford Waste Treatment Plant (WTP), also known as the vit plant, reached a major milestone when most of its cathodic protection system was placed into service last month. The cathodic protection system, which protects miles of underground piping from corrosion, is the last of three such WTP systems selected for early turnover from construction to …

continue story

Tests completed at Hanford’s Pretreatment Engineering Platform

Mon, February 9, 2009

Richland, Wash. — Installed and fully operational, the Department of Energy’s (DOE’s) Pretreatment Engineering Platform (PEP) is fulfilling its intended function – confirming the effectiveness and throughput of essential waste pretreatment processes for Hanford’s vitrification plant, also known as the vit plant. Advanced testing, known as phase one testing, began January 31, 2009, following completion of startup testing.

The …

continue story

Pretreatment Facility shield doors installed at Hanford Waste Treatment Plant

Wed, January 28, 2009

Richland, Wash. — Two massive shield doors were recently installed in the Pretreatment (PT) Facility at the Hanford Waste Treatment and Immobilization Plant (WTP), or vit plant, demonstrating steady construction progress. The 22-ton steel doors are each 10 feet high, 11 feet wide and approximately eight inches thick. Installed late last week and early this week, they are the …

continue story

Construction progresses on Hanford Waste Treatment Plant Pretreatment Facility

Tue, December 16, 2008

Richland, Wash. — The third elevation of concrete walls was recently completed on the Pretreatment (PT) Facility at the Hanford Waste Treatment and Immobilization Plant (WTP), demonstrating the continued progress on the WTP since full construction resumed in 2007. Construction was curtailed on the PT Facility and the High-Level Waste Facility in 2005 to address and finalize seismic design …

continue story

 <  1 2 3 4 >
Page 3 of 4